Johnstown #355 Restoration

 

September 28, 2002: While woodworking volunteers have (so far) avoided the camera, there is lots of activity refinishing and rebuilding components of Johnstown 355 which will be needed for its contract restoration. Here, a volunteer fights with one last hidden screw holding a piece of electrical gear.

 September, 2002
 

August 30, 2003:

While looking over 355's trucks, we discovered journal boxes on the #2 truck were not cleaned as well as desired. Each wheelset was therefore removed from the truck using our Burro crane. Journal boxes were removed from each wheelset, sandblasted, thoroughly cleaned, and then replaced. The journal bearings were then packed with new lubricator pads.

 August, 2003
 

August 23, 2003:

In conjunction with work to prepare Johnstown #355 for a move from Buehler Shop, its trucks were moved from Carbarn 2 back into Buehler Shop, where they will soon be placed under the carbody.

Although dusty, the trucks have rebuilt motors and new wheels and axles. The motor and journal bearings were never packed with wool waste, so those messy jobs are underway now.

At left, the trucks are shown entering Buehler Shop with the silhouette of #355 in the background.

 August, 2003
 

August 17, 2003:

With final paperwork submitted to PennDOT for bidding of work on car #355, we are preparing to move the car from the rear of Buehler Shop where it has resided for a long time.

Volunteers completed drilling dozens of new rivet holes and installing bolts which will temporarily hold the #2 end of the car together until further steelwork is completed.

 August, 2003
 

October 26, 2003:

Hard on the heels of our recent retrucking of Johnstown #355 (see below), our shop volunteers took on the ugly task of removing old motors from trucks which will go under our coming D-39 line car. Despite the tough nature of this job, our volunteers went into overtime and overdrive, and saw its completion in just one day.

 October, 2003
 

Large amounts of heat were applied to free bolts which have been rusting outside at another museum for many years.

Other items of importance were large wrenches, big hammers, prybars, and a crane.

 October, 2003
 October, 2003
 October, 2003
 

The jacking had to be carefully coordinated to prevent wracking (twisting) the car frame, which is relatively flexible.

 October, 2003
 

In actuality, it was securely supported on two lengths of 4x4 steel tubing. The height allowed plenty of clearance to easily move the trucks into place

 October, 2003
 

In the distance, a volunteer guides chains pulling the truck into place.

 October, 2003
 

Here the wisest volunteers puzzle over strategy for shifting the second truck from outside the truck...

 October, 2003